Barryton 900 x 675 1 rev

Barryton

Industry: Education
Location: Michigan
Sq Ft: 34100
Type: Tear-Off and Recovery
System: Duro-Last
  • Remove and dispose of the existing membrane roofing to deck.
  • Install one layer of recovery board underlayment to provide a smooth surface to accept the new membrane.
  • Mechanically fasten the Duro-Last single-ply membrane in accordance with Duro-Last requirements.
  • Flash all parapet and adjacent building walls.
  • At all perimeter edges bring the membrane over edge fastening 6” O.C.
  • Install new Duro-Last metal edging on all perimeter edges.
  • Flash all curbed units, stacks, chimneys, roof drains, and other penetrations.